The operating system, and in particular the scheduler, is perhaps the most important component.
Examples:
Control of laboratory experiments
Process control in industrial plants
Robotics
Air traffic control
Telecommunications
Military command and control systems
Correctness of the system depends not only on the logical result of the computation but also on the time at which the results are produced.
Tasks or processes attempt to control or react to events that take place in the outside world.
These events occur in "real-time" and tasks must be able to keep up with them.
Hard real-time task
One that must meet its deadline
Otherwise it will cause unacceptable damage or a fatal error to the system.
Soft real-time task
Has an associated deadline that is desirable but not mandatory
It still makes sense to schedule and complete the task even if it has passed its deadline.
Periodic tasks
Requirement may be stated as:
Once per period
Exactly
Aperiodic tasks
Has a deadline by which it must finish or start
May have a constraint on both start and finish time
5 requirements of the real-time operating systems:
Determinism
Responsiveness
User control
Reliability
Fail-soft operation
Concerned with how long an operaing system delays before acknowledging an interrupt.
Operations are performed at fixed, predetermined times or within predetermined time intervals.
The extent to which an operating system can deterministically satisfy requests depends on:
The speed with which it can respond to interrupts
Whether the system has sufficient capacity to handle all requests within the required time
Together with determinism make up the response time to external events.
Critical for real-time systems that must meet timing requirements imposed by individuals, devices, and data flows external to the system.
Concerned with how long, after acknowledgement, it takes an operating system to service the interrupt.
Responsiveness includes:
Amount of time required to initially handle the interrupt and begin execution of the interrupt service routine (ISR)
Amount of time required to perform the ISR
Effect of interrupt nesting
Generally much broader in a real-time operating system than in ordinary operaing systems.
It is essential to allow the user fine-grained control over task priority.
User should be able to distinguish between hard and soft tasks and to specify relative priorities within each class.
May allow user to specify such characteristics as:
Paging or process swapping
What processes must always be resident in main memory
What disk transfer algorithms are to be used
What rights the processes in various priority bands have
More important for real-time systems than non-real-time systems.
Real-time systems respond to and control events in real time so loss or degradation of performance may have catastrophic consequences such as:
Financial loss
Major equipment damage
Loss of life
A characteristic that refers to the ability of a system to fail in such a way as to preserve as much capability and data as possible.
Important aspect is stability.
A real-time system is stable if the system will meet the deadlines of its most critical, highest-priority tasks even if some less critical task deadlines are not always met.
The following features are common to most real-time OSs:
A stricter use of priorities than in an ordinary OS, with preemptive scheduling that is designed to meet real-time requirements.
Interrupt latency is bounded and relatively short.
More precise and predictable timing characteristics than general purpose OSs.
Real-time scheduling approaches depend on:
Whether a system performs schedulability analysis
If it does, whether it is done statically or dynamically
Whether the result of the analysis itself produces a scheduler plan according to which tasks are dispatched at run-time
Static table-driven approaches
Performs a static analysis of feasible schedules of dispatching.
Result is a schedule that determines, at run-time, when a task must begin.
Static priority-driven preemptive approaches
A static analysis is performed but no schedule is drawn up.
Analysis is used to assign priorities to tasks so that a traditional priority-driven preemptive scheduler can be used.
Dynamic planning-based approaches
Feasibility is determined at run-time rather than offline prior to the start of execution.
Dynamic best effort approaches
No feasibility analysis is performed
System tries to meet all deadlines and aborts any started process whose deadline is missed.
Static table-driven scheduling
Applicable to tasks that are periodic
Input to the analysis consists of the periodic arrival time, execution time, periodic ending deadline, and relative priority of each task.
This is a predictable approach but one that is inflexible because any change to any task requirements requires that the schedule be redone.
Earliest-deadline-first or other periodic deadline techniques are typical of this category of scheduling algorithms.
Static priority-driven preemtive scheduling
Makes use of the priority-driven preemptive scheduling mechanism common to most non-real-time multiprogramming systems.
In a non-real-time system, a variety of factors might be used to determine priority.
In a real-time system, priority assignment is related to the time constraints associated with each task.
One example of this approach is the rate monotonic algorithm which assigns static priorities to tasks based on the length of their periods.
Dynamic planning-based scheduling
After a task arrives, but before its execution begins, an attempt is made to create a schedule that contains the previously scheduled tasks as well as the new arrival.
If the new arrival can be scheduled in such a way that its deadlines are satisfied and that no currently scheduled task misses a deadline, then the schedule is revised to accommodate the new task
Dynamic best effort scheduling
The approach used by many real-time systems that are currently commercially available.
When a task arrives, the system assigns a priority based on the characteristics of the task.
Some form of deadline scheduling is typically used.
Typically the tasks are aperiodic so no static scheduling analysis is possible.
The major disadvantage of this form of scheduling is, that until a deadline arrives or until the task completes, we do not know whether a timing constraint will be met.
Its advantage is that it is easy to implement.
Can occur in any priority-based preemptive scheduling scheme.
Particularly relevant in the context of real-time scheduling.
Occurs when circumstances within the system force a higher priority task to wait for a lower priority task.
Unbounded priority inversion:
The duration of a priority inversion depends not only on the time required to handle a shared resource, but also on the unpredictable actions of other unrelated tasks.
e.g., The "Mars Pathfinder" mission.
Stallings, W. (2018). Operating Systems: Internals and Design Principles (9th ed.). Pearson Education, Inc.